About Us

A 110 bed modern hospital in Metropolis road, Tagbak, Jaro, Iloilo City.

 A. THE BEGINNINGS

    Sometime in 1997, Dr. Angelo “Anji” and Dr. Ma. Mercedita “Lana” Alcala opened the idea of building a hospital for the Ilonggos to Dr. Evelyn “Bukay” Lozada, Dr. Roberto “Bob” Lozada and later on to Dr. Danilo “Dan” Encarnacion. Except for Dr. Bob the four were very close friends being classmates in West Visayas State College of Medicine. Drs. Anji & Lana wanted to share their experience, having been involved in the building of several hospitals in Metro Manila.

The idea did not materialize until 14 years later when idea to build a hospital owned by doctors from Iloilo was revived. The first step taken was the formation of a core group of physicians that would be involved in the initial planning. The members were Dr. Angelo Alcala, Dr. Mercedita Lana, Dr. Danilo Encarnacion, Dr. Evelyn Lozada, Dr. Roberto Lozada, Dr. Roland Uy, Dr. Anton Juan Loa, Dr. Myrna Ong and Dr. Chester Jardiolin. Eventually, other members were recruited to complete the 15 members of the Board and they were – Dr. Danilo Valencia, Dr. Jesse Uy, Dr. Erwin Dulos, Dr. Segundo Anayan, Dr. Hannah Jabasa and Dr. Perpetua Socorro Barrera.
    It was decided that the “founders” or major stockholders that would be recruited will be limited to 75 physicians that were actively practicing. Even the common shares were first offered to practicing physicians. They were expected to refer patients to the hospital in the future.

    The first general assembly on April 9, 2013 was held at Alicia’s in Pavia. Here, the roadmap to building the hospital was clearly explained by Dr. Encarnacion who was leading the group. The guidance of Drs. Anjie and Lana Alcala who talked about their personal experiences visibly reassured the members that although it was a daunting undertaking it was a doable task. The initial steps of attaining the dream was put into motion with the election of the interim members of the board. The group acquired a legal entity when its by-laws was approved by Securities and Exchange Commission on June 25, 2013. From then on the group was known as Metro Iloilo Hospital and Medical Center Inc. The first Board meeting was conducted on July 9, 2013, at Luna 101, Sarabia manor Hotel. It was during this meeting that the officers were elected namely: Dr. Roland L. Uy – Chairman, Dr. Antonio S. Juan Loa- Vice Chairman, Dr. Danilo A. Encarnacion – President, Dr. Chester H. Jardiolin - Executive Vice President, Dr. Roberto S. Lozada - Corporate Secretary, Dr. Myrna Ong – Asst Corporate Secretary, Dr. Evelyn Socorro S. Lozada- Treasurer and Ast. Treasurer - Dr. Perpetua Socorro Barrera.

     Board members were: Dr. Angelo Alcala, Dr. Mercedita Alcala, Dr. Danilo Valencia, Dr. Jesse Uy, Dr. Erwin Dulos, Dr. Segundo Anayan and Dr. Hannah Jabasa. Later on the official seal designed by Dr. Jesse Uy was adopted by the corporation.

 B. THE ACQUISITION OF LOTS

     The hospital’s location was crucial. It was decided that it would be somewhere in Jaro away from the cluster of hospitals in the city. After months of searching, two adjacent lots totaling 4,790 sq. m at the Metropolis road at Tagbak, Jaro was acquired on August 2014. It was an ideal location because it was very accessible being a few meters away from the national road going to Leganes. Additional adjacent lots 2,092 sq. m at the side and 6,090 sq. m at the back were subsequently acquired on August 2015 and January 2016 respectively bringing the total area to 1.2 hectares.

 C. THE SELECTION OF ARCHITECT & PROJECT MANAGER

     The hospital’s location was crucial. It was decided that it would be somewhere in Jaro away from the cluster of hospitals in the city. After months of searching, two adjacent lots totaling 4,790 sq. m at the Metropolis road at Tagbak, Jaro was acquired on August 2014. It was an ideal location because it was very accessible being a few meters away from the national road going to Leganes. Additional adjacent lots 2,092 sq. m at the side and 6,090 sq. m at the back were subsequently acquired on August 2015 and January 2016 respectively bringing the total area to 1.2 hectares.

 D. PREPERATIONS FOR THE CONSTRUCTION

     The hospital’s location was crucial. It was decided that it would be somewhere in Jaro away from the cluster of hospitals in the city. After months of searching, two adjacent lots totaling 4,790 sq. m at the Metropolis road at Tagbak, Jaro was acquired on August 2014. It was an ideal location because it was very accessible being a few meters away from the national road going to Leganes. Additional adjacent lots 2,092 sq. m at the side and 6,090 sq. m at the back were subsequently acquired on August 2015 and January 2016 respectively bringing the total area to 1.2 hectares.

     On March 2, 2015, the permit to construct of a level 2 hospital was given the go signal by the Department of Health (DOH). In a special general assembly on July 19, 2015, it was explained that the cost of the original design of a 7 storey building with 177 bed capacity would be too high. Instead, a scaled down 6 storey building with a floor area of 7,895 sq. meters with a smaller footprint was presented. The new design that reduced the estimated cost by 30% was unanimously approved. The ancillary building with a floor area of 1,059 sq meters was added on January 26, 2017. This would house the dietary, rehabilitation medicine, conference rooms and dining area. In the following months the site was cleared and flattened with bulldozers. The soil was tested. Based on the soil analysis, numerous end bearing concrete rectangular piles were methodically embedded to the ground to create a steady support for the structures above to be built. Temporary fence was constructed to isolate construction site.

 E. CONSTRUCTION PHASE

     The project manager presented a list of several building contractors. In a clear matrix form, they were rated according to the parameters of the Philippine Contractor Accreditation Board (PCAB). The Board decided to award the major structural contract to JITS Construction Corporation on December 2015. The first concrete pouring was done on March 3, 2016 attended by members of the Board. From then on the construction of the main building accelerated. On May 2, 2016 a joint meeting with the architect, main structural contractor and the Board was held to assess the progress of works which was found to be satisfactory and within the set time frame.

    A loan agreement was obtained from Development Bank of the Philippines to partly fund the building and the medical equipment . This was formalized through a contract signing on August 8, 2016.

 F. PREPARATION FOR RUNNING THE HOSPITAL

    A. Founders Enroll in Masteral Class The hospital is partly a business enterprise. To empower the members, they enrolled in a 2 year post graduate course – Masters in Hospital Management (MHM) acredited by CHED. This was offered by Health Care Executives headed by Dr. Jose Pepvbito Amores at St. Joseph School based in Quezon City. Special arrangement was made wherein various instructors came twice a month in Iloilo City to conduct classes which officially started on June 28, 2015 at SV More Building. Finally, all the 28 enrollees successfully completed the course.

    B. Strategic Planning The founders embarked on a workshop at Hotel del Rio on 5/17/16 and 7/5/16 to draft the Mission and Vision, Core values and other guiding principles unique to the hospital.

    C. Creation of Clinical Departments On June 2017, the board created the clinical departments, appointed the chairs and the medical director. The therapeutics and pharmacy committees were likewise created to prepare the hospital formulary. Numerous meetings were held in the temporary office at the St. Elizabeth building to prepare the guidelines of each department.

 G. THE ROAD TO COMPLETION

    On December 10 2017, a general assembly and Christmas party was held for the first time in the newly completed 3rd floor which would soon house the out patient clinics and laboratory. It was poignant, emotional and happy occasion participated by the founders and the growing staff of employees. The official address of the corporation was changed to MIHMCI Hospital, Metropolis Road, Tagbak Jaro.

    B. Strategic Planning The founders embarked on a workshop at Hotel del Rio on 5/17/16 and 7/5/16 to draft the Mission and Vision, Core values and other guiding principles unique to the hospital.

    C. Creation of Clinical Departments On June 2017, the board created the clinical departments, appointed the chairs and the medical director. The therapeutics and pharmacy committees were likewise created to prepare the hospital formulary. Numerous meetings were held in the temporary office at the St. Elizabeth building to prepare the guidelines of each department.

    There was a flurry of activities. These were all geared towards obtaining the permit from DOH. By March almost all the structural works and finishing were complete. In April 17, 2018, a team from Department of Health visited and evaluated the Hospital. They made several structural and functional suggestions which were fully addressed. After two months a second visit was made on June 17. After a thorough evaluation by DOH head office, the License to Operate was given on July 5, 2018. The OPCC, together with the laboratory, pharmacy and diagnostic services commenced operation on July 9. The grand opening was held on July 17 and accepted patients starting July 18, 2018.

 H. THE NOVELTIES

    The newly completed hospital is full of innovations. It is first and only hospital that has: 1) computer-controlled pneumatic tube system to deliver drugs, documents and specimens to and from laboratories, nurses’ stations and payments to the cashier; 2) fully integrated computerized electronic health record system; 3) OPCC or out patient clinical care for out patients - composed of 40 multi-specialty clinics with adjacent laboratory unified in one floor; 4) a scenic elevator which would transport patients directly from the ground to the 3rd floor OPCC; 5) free wi-fi through local area network which would allow wireless connection to the internet; and 6) wide parking spaces that could accommodate more than 200 vehicles.

 I. THE 75 FOUNDING PHYSICIANS

    This was a unique concept in Iloilo. Instead of constructing the infrastructure first, the pool of doctors who will support the Hospital were recruited from the start and involved in the decision making. Initially, it was a leap of faith for the major investors or founders who took the risk and believed that the dream could be realized. These doctors and corresponding specialty were:

View the founders
 

Testimonial

    It is with great pride and honor that I stand before you today on this momentous occasion. Today marks the realization of our dream of building a hospital. We have toiled a lot, spent sleepless nights with untiring efforts for the last three years in order to come up with what we have now.

    I would like to recognize the efforts shared by my fellow core members as well as the support from our investors without which this dream would not be realized. the momentum is now with us, the process of building will continue, the pursuit for success still lies ahead. We have just begun, and we will strive further. Together we must work unmindful of personal gains, for a common good, for the good of this hospital.

    So i encourage my fellow Founders, that we must do our part in making this hospital as the shining glory of our efforts for ourselves, our family, our community and most of all for the God Almighty.

    Thank you very much.

Encarnacion, Danilo A., MD - Internal Medicine, Gastroenterology
President, Metro Iloilo Hospital & Medical Center

Good morning, friends and colleagues! Today marks another milestone in our journey to a more progressive and fruitful administration of our beloved Metro Iloilo Hospital and Medical Center, Inc.

In today’s modern world, the maintenance of a corporate website is indispensable. With information at our fingertips, our online presence translates to client convenience. It is through our website that our customers are able to find us 24/7, anytime, anywhere.

In our bid to be more progressive, through the creation of our new website, we hope to achieve the following:

Firstly, we hope to improve our traffic by providing our clients with an easier way of communicating to us by adding functionality and a more integrated and user-friendly interface;

Secondly, we aim to improve our credibility with our new design. A good-quality, easy-to-use website would surely make our clients feel more comfortable using our service. The aim is for our clients to assume that they can expect that same positive experience through our actual care when they are physically within our premises; and

Finally, in general, we hope to provide a place that potential clients and stakeholders can be referred to. It will show what our hospital is about, what is has achieved, and what it can achieve in the future.

I hope that we all continue to support these types of initiatives for a more successful Metro Iloilo Hospital and Medical Center, Inc. Thank you and stay safe always!

Valencia, Danilo V., MD - Internal Medicine, Gastroenterology